Published11 May 2026Updated9 July 2026
Eight weeks is what the rules say. Reality tends to disagree. We break down actual planning timescales for every type of project — so you can plan your build with something approaching confidence.
Eight weeks is the statutory target the government sets for most planning applications. It's also, for a lot of projects, about as reliable as a British summer.
Eight or thirteen weeks. That's the statutory target the government sets for most planning applications. It's also - for many projects - about as reliable as a weather forecast. Sometimes it holds. Often it doesn't. And if you're planning a project around that number without understanding what can shift it, you're setting yourself up for frustration and, more likely, cost.
Here's the honest picture - for every type of project, from a small rear extension to a large commercial development - along with the factors that stretch timescales and what you can do to keep things on track.
Before asking how long it takes, it's worth being clear on which route you're using. There are several different application types, each with its own statutory clock:
Knowing which route you're on matters. The clock doesn't even start the same way for all of them, and 'validation' (when the clock officially begins) is itself something most people don't realise sits outside the 8 weeks.
For a standard householder application - a rear extension in a residential area, a loft conversion, a garden building - 8 weeks is achievable when:
Where it slips: Incomplete applications get returned for more information. Conservation areas attract more scrutiny and objections. And planning departments across the Midlands vary considerably in caseload and processing speed - some are reliably within 8 weeks, others are routinely running at 12–14 weeks for routine householder work.
The validation gap is the one that catches people most often. Your application isn't formally 'in' until the council validates it - which can take a week or two after submission. That time doesn't count toward the 8 weeks. Build it into your programme from day one.
A single new dwelling on an uncontested plot might reach a decision inside 10–12 weeks. In practice, most significant residential applications - especially where design quality, site access, or the principle of development are factors - take longer.
For multi-unit schemes - apartment conversions, HMOs, small housing developments - assume 13 weeks as your baseline, with extensions possible when:
Self-build projects vary enormously. A replacement dwelling in a straightforward location might come through in 10 weeks. A self-build in a conservation area, adjacent to a listed building, or involving a striking contemporary design in a traditional setting will take longer - and should be planned that way from the start.
Commercial planning is a different discipline from residential. Case officers are assessing a different set of material considerations - employment impact, parking, servicing, viability, and in mixed-use schemes, the effect on residential amenity.
Typical commercial scenarios and realistic timescales:
Change of Use (office to residential, retail to HMO)
8–13 weeks, depending on scale and whether Prior Approval offers a faster alternative route. Several permitted development rights for change of use were significantly expanded in 2021; understanding whether Prior Approval or full planning is the right route matters for timescale.
HMO Applications
8–13 weeks in most Midlands authorities. Be aware that several councils in this region have introduced Article 4 directions removing permitted development rights in specific areas - which affects both the route available and the evidence required. Check the position in your local authority before assuming the faster route is open to you.
Co-Living, PBSA, and Larger Conversions
13+ weeks, usually longer. These applications require more supporting documentation - transport assessments, management plans, noise assessments, often viability appraisals - and are more likely to go to committee rather than delegated decision.
Commercial New Build
13 weeks as a baseline. Realistically, 16–20+ weeks for anything with complexity - retail, industrial, mixed-use. The more consultees involved (Highways, Environment Agency, Historic England, utility companies), the harder it is to contain the timetable.
The most important thing with commercial applications isn't just the headline timescale - it's identifying which supporting documents will be required before you submit. Discovering you need an ecology survey or Transport Statement after a live application is registered adds weeks of delay that pre-application advice would have avoided.
Beyond site designations, these are the most common timescale-extending factors across all project types:
Getting planning permission is not always the same as being able to start work.
Most decisions come with pre-commencement conditions - things that must be formally resolved before building work can begin. These vary by project but typically include:
• Materials approval
• Drainage or sustainable drainage details
• Archaeological watching brief requirements
• Ecological management plans
• Highway construction details
Each condition requires a formal discharge application. Discharge applications have their own determination target - 8 weeks. On a complex project, working through pre-commencement conditions can add 2–3 months before a spade goes in the ground.
Factor this into your programme from the start, not as a surprise at the end. The architects who set realistic timelines build condition discharge into the original project programme - not as an afterthought.
The most reliable way to keep a planning application on track is doing the right groundwork before submission. None of what follows is complicated. But it separates applications that flow from ones that stall.
Most Midlands planning authorities offer a paid pre-application service - a meeting or written response from a planning officer before formal submission. Done well, this surfaces objections and issues before they derail a live application. It's not always worth the cost on a straightforward householder application, but for anything complex, it's time well spent.
Know which supporting documents are required and have them ready before submission. An application submitted with everything in order is validated faster and assessed faster. The cost of getting this right is far lower than the cost of the delay when you get it wrong.
Understanding how a particular planning department thinks - what they'll push back on, which design approaches they respond to, which arguments land with which officers - isn't something you learn from a textbook. It comes from 700+ applications submitted across the Midlands over more than 20 years.
JSA has a 97% planning approval rate over the last 6 years. That figure is the result of preparing applications that address the issues before they become problems - and understanding the difference between what the policy says and how it gets applied in practice.
JSA Architects Across the Midlands
We work with homeowners, developers, and landlords across the Midlands. Fees, planning authorities, and project types vary by location — find local insight and project examples for your area:
Architects in Derby → — Quarndon, Kirk Langley, Duffield, Allestree, Darley Abbey, Mickleover, Littleover
Architects in Nottingham → — The Park Estate, West Bridgford, Edwalton, Mapperley Park, Wollaton, Bramcote
Architects in Lichfield → — Shenstone, Little Aston, Four Oaks, Streetly, Aldridge, Walsall, Tamworth, Whittington
Architects in Solihull → — Knowle, Dorridge, Hampton in Arden, Shirley, Dickens Heath, Olton
Architects in Sutton Coldfield → — Four Oaks, Wylde Green, Boldmere, Mere Green, Streetly, Little Aston
faq's
Articles